How long a remodeling permit takes in Portland in 2026

Portland sets itself 7 days for the first review of a residential alteration and 15 for an addition. Those are goals for one stage of three. This page lays out the stages, and puts the city's figures beside the ones the towns around it publish.

Talk to Don about your projectHe comes out and prices it himself
5.032 Google reviews
Oregon CCB
#208048
Washington L&I
#DWVCOCL754OW
Coverage
General liability insurance
Established
2008

The stages a Portland permit goes through.

The review time people quote covers the middle of it. A permit is issued only when the last stage is done.

A new detached building framed and sided on its slab

Intake

The city first checks that the application is complete. Applications are taken in the order they arrive. One that is missing something comes back with a list. Review starts once the application is accepted.

New beam framing before the walls are closed

First review

Portland's goal for the first technical review of a house is 7 days for an alteration and 15 days for an addition or a new building. The city says current workload can move those figures.

A kitchen wall opened with insulation and wiring exposed

Checksheet and second review

A first review ends in an approval or a checksheet, the reviewer's list of what is missing. Every item has to be answered. The city's goal for the review that follows is 5 to 7 days.

New concrete stem walls with the anchor bolts set beside an older house

Pre-issuance

A last check before the permit is issued, taken in the order of the final sign-off. Changes made to the plans during review are the usual cause of delay here.

What each city publishes.

Each line is the city's own figure, as its page stood on November 20, 2026. A published time is a target for a complete application.

  • PortlandFirst review in 7 days for an alteration and 15 for an addition. Second review in 5 to 7 days. Goals, not promises.
  • Lake OswegoFirst review of a residential permit in two to three weeks, by the city's July 2026 estimate.
  • TualatinTwo to six weeks for a residential permit. Up to two business days for one issued over the counter.
  • West LinnNo figure for building permits. A tree removal permit can take up to 30 business days.
  • TigardNo figure for building permits. Most tree permits are processed within 10 days.
  • Happy Valley, Milwaukie, BeavertonNo review time on the pages we read. The building office gives a current one by phone.

They handled all the necessary permits.

“We hired DWV Construction to remove an existing detached (deteriorating) garage and plan/build a new one. The process was easy and painless from start to finish. They helped us decide on the design and placement of the new garage, handled all the necessary permits and guided us through the whole process. Every team that came on-site was functional, professional and left the property in better condition than when they arrived. We were kept informed and in communication throughout, making us feel confident and at ease. We are so happy with our new garage!”

Kelley BarryGoogle review

Common questions.

  • The city's goal is a first review within 7 days for a residential alteration and 15 days for an addition, and it says workload can change that. Review is one of three stages. On a whole home remodel, design, engineering and permits together can take two to six months before construction.

    A new detached building framed and sided on its slab

Talk directly to Don about your project.

Or pick a time for Don's site walk

★★★★★
“In the end our project was completed ahead of schedule, on budget and we are completely pleased with the result.”
Craig Cotugno · Google review