How long a remodeling permit takes in Portland in 2026
Portland sets itself 7 days for the first review of a residential alteration and 15 for an addition. Those are goals for one stage of three. This page lays out the stages, and puts the city's figures beside the ones the towns around it publish.
Talk to Don about your projectHe comes out and prices it himself- Oregon CCB
- #208048
- Washington L&I
- #DWVCOCL754OW
- Coverage
- General liability insurance
- Established
- 2008
The stages a Portland permit goes through.
The review time people quote covers the middle of it. A permit is issued only when the last stage is done.

Intake
The city first checks that the application is complete. Applications are taken in the order they arrive. One that is missing something comes back with a list. Review starts once the application is accepted.

First review
Portland's goal for the first technical review of a house is 7 days for an alteration and 15 days for an addition or a new building. The city says current workload can move those figures.

Checksheet and second review
A first review ends in an approval or a checksheet, the reviewer's list of what is missing. Every item has to be answered. The city's goal for the review that follows is 5 to 7 days.

Pre-issuance
A last check before the permit is issued, taken in the order of the final sign-off. Changes made to the plans during review are the usual cause of delay here.
What each city publishes.
Each line is the city's own figure, as its page stood on November 20, 2026. A published time is a target for a complete application.
- PortlandFirst review in 7 days for an alteration and 15 for an addition. Second review in 5 to 7 days. Goals, not promises.
- Lake OswegoFirst review of a residential permit in two to three weeks, by the city's July 2026 estimate.
- TualatinTwo to six weeks for a residential permit. Up to two business days for one issued over the counter.
- West LinnNo figure for building permits. A tree removal permit can take up to 30 business days.
- TigardNo figure for building permits. Most tree permits are processed within 10 days.
- Happy Valley, Milwaukie, BeavertonNo review time on the pages we read. The building office gives a current one by phone.
They handled all the necessary permits.
“We hired DWV Construction to remove an existing detached (deteriorating) garage and plan/build a new one. The process was easy and painless from start to finish. They helped us decide on the design and placement of the new garage, handled all the necessary permits and guided us through the whole process. Every team that came on-site was functional, professional and left the property in better condition than when they arrived. We were kept informed and in communication throughout, making us feel confident and at ease. We are so happy with our new garage!”
Kelley BarryGoogle reviewCommon questions.
The city's goal is a first review within 7 days for a residential alteration and 15 days for an addition, and it says workload can change that. Review is one of three stages. On a whole home remodel, design, engineering and permits together can take two to six months before construction.

Three things, by the city's own account. An application that is not complete at intake. A checksheet with items left unanswered, since every item on every checksheet has to be answered. And changes to the plans while they are under review.
Some of the city's plan review groups accept a request for Applicant Paid Overtime, to review a project ahead of its due date. The city says the request does not guarantee an earlier review.
Oregon adopted its 2026 residential code on October 1, 2026. Until March 31, 2027 an applicant may file under the 2023 edition or the 2026 edition. From April 1, 2027 a residential permit has to follow the 2026 edition.
In Clackamas County they do not. The county's electrical, plumbing and mechanical permits are issued without plan review. The licensed electrician and plumber on the job file them.
It differs town by town, and not every town says. Lake Oswego put first review at two to three weeks in July 2026. Tualatin lists two to six weeks. West Linn and Tigard publish no time for a building permit.
DWV files the building permit, handles the corrections the city asks for and books the inspections. The licensed electrician and plumber file their own permits, as Oregon requires.
Where the rules on this page come from
- City of Portland: check permit status and review timeframes
- City of Portland: new residential codes took effect October 1
- City of Lake Oswego: plan review and inspection times, July 2026
- City of Tualatin: permits and turnaround times
- City of West Linn: tree removal permit
- City of Tigard: tree permits
Read November 2026. Rules change, and the office that issues your permit has the last word.